Jefferson Township mayor provides update on Route 15 northbound, Weldon Road bridge closures as emergency repairs continue
JEFFERSON TOWNSHIP, N.J. (Morris County) — Emergency repairs and underground investigations continued Saturday as officials worked to determine when Route 15 northbound and the Weldon Road bridge could safely reopen following closures caused by a large hole near the bridge abutment, according to Jefferson Township Mayor Eric Wilsusen.
In a Nov. 21 update, Wilsusen said crews worked overnight to fill the hole with large rocks to stabilize the area. New Jersey Department of Transportation officials believe the material is holding, and crews have begun pumping concrete to provide additional stabilization.
Wilsusen, who arrived at the site around 8:30 a.m. Saturday, said he met with NJDOT Commissioner Priya Jain and other officials to review the emergency repairs, assess progress and discuss the next steps toward reopening the roads.
According to the mayor, the Weldon Road bridge has been continuously monitored for signs of movement, and none has been detected. However, additional geotechnical investigations are being arranged to evaluate the condition and stability of the bridge foundations.
The bridge will remain closed until all necessary engineering evaluations and safety inspections are completed and NJDOT determines it is safe to reopen, Wilsusen said.
Meanwhile, geotechnical surveys were conducted overnight along Route 15 northbound to evaluate the roadway and the ground beneath it. NJDOT expects the results of those investigations to be available by Monday, Nov. 23.
Crews are also using boring equipment to conduct additional subsurface investigations to identify possible underground voids or water that could affect the roadway’s stability.
Once those investigations are completed, NJDOT engineers will assess the roadway base and determine whether any portion of Route 15 northbound can safely reopen to traffic.
Wilsusen said there is currently no confirmed timeline for reopening either roadway.
The mayor also raised concerns about the impact of the closures on school transportation if they continue into the upcoming week.
Members of his administration and the school superintendent’s staff are scheduled to meet Sunday, Nov. 22, to discuss transportation arrangements and develop a plan to minimize disruptions for students and families.
Wilsusen said he has also been working with state Sen. Anthony Bucco to address traffic concerns, particularly for residents of the Lake Shawnee community, who are facing lengthy detours.
The mayor said he urged NJDOT to consider establishing a temporary crossover lane or alternative traffic pattern that would allow vehicles to travel in both directions if Route 15 northbound must remain closed for an extended period.
Such an arrangement would depend on whether it could be implemented safely, he said.
Wilsusen, who lives in Lake Shawnee, said he understands the difficulties residents are experiencing because of the closures and believes additional traffic alternatives must be considered if repairs take longer than expected.
The mayor also drove the Edison Road detour Saturday to evaluate traffic conditions. He described the detour as manageable, although adjustments are being made, and advised motorists to avoid the area if possible.
According to Wilsusen, the next 24 to 48 hours will be important as NJDOT continues its investigations and evaluates the information collected.
He said he hopes officials will have a clearer understanding by Monday of the extent of the damage, necessary repairs and a potential timeline for reopening at least part of Route 15 northbound.
Wilsusen thanked NJDOT crews, emergency personnel, contractors, township and state employees, Bucco, Assemblywomen Aura Dunn and Marisa Sweeney, and residents for their assistance and patience during the ongoing emergency.
The mayor said he will continue monitoring the situation and provide additional updates as information becomes available.