More than $13 million in contracts awarded for I-78 Toll Bridge painting and repairs in 2027
PHILLIPSBURG, N.J. (Warren County) — The Delaware River Joint Toll Bridge Commission has awarded more than $13 million in contracts for a painting and repair project at the Interstate 78 Toll Bridge, marking the first time the twin-span bridge will be repainted since it opened 37 years ago.
The project, scheduled for 2027, will include cleaning and painting the bridge’s steel structures, along with steel repairs, drainage work and improvements to approach bridges along the commission’s I-78 roadway segments in New Jersey and Pennsylvania.
The bridge, which opened Nov. 21, 1989, still has its original paint.
Commission members approved the contracts during their monthly meeting Nov. 23 in Lower Makefield, Pennsylvania. The painting and repair contract was awarded to Anselmi & DeCicco Inc. of Maplewood, New Jersey, for an amount not to exceed $11,655,265.
A corresponding construction management and inspection contract was awarded to STV Inc. of Lawrenceville, New Jersey, for an amount not to exceed $1,553,970.31.
Construction activities are expected to include:
- Cleaning and painting the seven-span twin bridge steel superstructures over the Delaware River.
- Performing steel repairs where necessary.
- Replacing drain troughs at the river bridge’s abutments.
- Repairing cracks and deteriorated concrete on the decks and substructures of the river bridge and its approach bridges.
- Applying epoxy waterproof coatings to bridge seats throughout the commission’s I-78 jurisdiction.
- Repairing deteriorated slopes along the commission’s I-78 roadway segments.
- Resetting rocker bearings where necessary on the river bridge and its approach bridges.
- Resealing bridge deck joints throughout the commission’s I-78 jurisdiction.
The I-78 Toll Bridge is the commission’s most heavily traveled river crossing and serves as an important interstate connection between North Jersey port facilities and warehouses in Pennsylvania’s Lehigh Valley and areas farther south, west and north.
Planning for the project stems from deficiencies identified in the commission’s 2025 Annual Maintenance Report and subsequent field inspections conducted by engineering and capital program management consultants.
Project preparation activities are expected to begin in January 2027, followed by cleaning and painting. Drainage-related work is expected to take place later.
Motorists should anticipate a series of lane and shoulder closures throughout the project. The commission said specific details regarding travel impacts will be announced as they become available in 2027.
The project is expected to be completed by the end of 2027 if work proceeds as planned.